arrival date

The date purchased material is due to arrive at the receiving site. The arrival date can be input, it can be equal to the current due date, or it can be calculated from the ship date plus transit time. See: due date.

1) In activity-on-arrow networks, the graphic presentation of an activity. The tail of the arrow represents the start of the activity. The head of the arrow represents the finish. Unless a timescale is used, the length of the arrow stem has no relation to the duration of the activity. Length and direction of the arrow are usually a matter of convenience and clarity. 2) In activity-on-node networks, an arrow represents a precedence requirement.